Bulldog Automation: Rear Quarter

product

  • Rear Quarter Weld Assembly

Challenge

  • Coherix 3D inspection integration into sealer systems to ensure dispense beads align with customer specifications.
  • Comprehensive cycle time analysis to guarantee geo-set & buffer stations met required cycle time.
  • Despite a delay from the OEM, our dedicated team has successfully adhered to the original project dates committed to the customer

Processes:

  • 80 KUKA Robots between LH & RH cell
  • Resistance Welding
  • Adhesive Dispense
  • Projection Nut Welding
  • Projection Stud Welding
  • Drawn Arc Stud Welding
  • Material Handling

Cycle Time:

  • 59.58s cycle time
  • Main line footprint: 18,684 ft